Cooling and water

How much water does a data center use? It depends on one choice.

Almost every watt of electricity entering a data center turns into heat that must be moved outside, around the clock. How the building sheds that heat — by evaporating water, or by fans and sealed liquid loops — determines whether it drinks millions of gallons a day or roughly what an office park does. For the same 30 MW facility, the difference between cooling designs is about fifty-fold.

The cooling systems, plainly

  • Open cooling towers (evaporative) — warm water is sprayed through outdoor towers; evaporation carries the heat away. Energy-efficient, but the thirstiest design: roughly 6.75 million gallons per year per megawatt, per Uptime Institute.99Some water is also regularly discharged to the sewer as “blowdown” to flush out concentrated minerals.100
  • Air-cooled (dry) systems — giant radiator-and-fan units reject heat straight to the air. Near zero water, but more electricity (evaporative assist can cut peak-summer cooling electricity 10–35%) and more fan noise.113
  • Direct evaporative (“swamp cooler”) — outside air is cooled through wetted media. Uses far less water than open towers; Meta’s version runs about a tenth of traditional consumption.99
  • Adiabatic / hybrid — dry coolers that mist water only on the hottest days. Low, seasonal water use.99
  • Closed-loop, direct-to-chip liquid cooling — the new AI-era standard. A sealed water loop is filled once at construction and recirculated indefinitely; Microsoft says its zero-water-for-cooling design avoids more than 125 million liters (~33 million gallons) per facility per year, leaving only restroom-scale water use.101
  • Immersion cooling — servers submerged in non-conductive fluid; essentially no on-site water. Still niche (crypto, HPC).99

What that means for a 25–30 MW facility

Using published water-efficiency figures (WUE — liters of water per kilowatt-hour of computing), here is the computed range for a 30 MW facility running at full load. These are estimates from cited inputs, not the developer’s numbers — the actual figure depends entirely on the cooling design the end user chooses.

Open cooling towers (Uptime benchmark)~554,000 gal/day
Evaporative, industry-average WUE (1.8 L/kWh)~342,000 gal/day
Modern efficient fleet (0.27–0.30 L/kWh, Microsoft FY25)~52,000–57,000 gal/day
Meta-style direct evaporative (0.20 L/kWh)~38,000 gal/day
Closed-loop / air-cooled (“zero water” design)~8,000–23,000 gal/day

Math: 30 MW × 8,760 hours = 262.8 million kWh/yr; multiply by the cited WUE and convert liters to gallons. WUE inputs: Uptime Institute,99 industry average,99 Microsoft,101 Meta.102The closed-loop row uses Microsoft’s real Wisconsin facility: 2.8M gallons/yr in Phase 1, ~8.4M gallons/yr at later phases.107

For comparison: Google disclosed that its average data center campus used about 450,000 gallons per day in 2021103 — so a worst-case evaporative 30 MW build would behave like a typical Google campus, while a closed-loop build would use about as much water as a large office park.107

What Pikeville has said about water

The city operates its own municipal water system, drawing from the Levisa Fork, and says that based on the usage the developer has described, the system can comfortably meet the requirement — with the projections being independently verified, and with an already-approved withdrawal permit whose capacity is well above projected needs.2 The key questions worth asking as details emerge: which cooling design the end user will commit to in writing, what the peak summer-day demand is (academic modeling finds peak-day demand ~3.6× the average is what stresses small municipal systems),114 and how cooling-tower blowdown, if any, will be handled at the wastewater plant.100

The trade-off, honestly

Water and electricity trade against each other. Evaporating water is the cheapest way (in energy) to shed heat; going dry costs more electricity.113 Google has argued water-cooling cuts its energy use about 10% versus air cooling.103There’s also a hidden ledger: peer-reviewed research found that roughly 75% of data centers’ total water footprint is indirect — consumed by the power plants generating their electricity, not at the site itself.104A “zero-water” data center still drives water use somewhere on the grid. Nationally, data centers consumed about 66 billion liters (~17 billion gallons) directly in 2023, a figure the federal LBNL report projects could double or quadruple by 2028.11 The industry trend helps here: AI chips run too hot for air alone, so new builds increasingly use sealed direct-to-chip loops — which happen to nearly eliminate on-site water use.101

Can the waste heat be put to use? Yes — with honest caveats

Nearly all electricity entering a data center leaves as heat, so a 25–30 MW facility is also, in effect, a 24/7 heat source of roughly the same size. In Northern Europe, where cities have district heating networks, that heat genuinely warms homes: Meta’s Odense, Denmark plant recovers heat for the city network (about 45 MW of heat production serving thousands of homes and a hospital),116Microsoft’s data centers near Helsinki now supply up to 180 MW of district heat — on track to cover ~40% of heating demand for an area of 250,000 people,117Google’s Hamina facility will cover up to 80% of its town’s heating demand free of charge,118and Stockholm’s utility literally pays data centers for their heat.119 Germany now requires new data centers to reuse 10–20% of their energy as heat.125

The honest catch: data center exhaust is low-grade heat — roughly 100°F air from air-cooled halls (hotter, more usable 50–60°C water from modern liquid-cooled designs)124 — and using it requires heat pumps plus, crucially, a heat customer nearby. The Nordic projects work because city-wide hot-water networks already existed; almost no U.S. town has one,123 and we found no documented example of a small-city American data center heating homes.

What isprecedented in the U.S. is single-neighbor reuse: Amazon’s Seattle towers are warmed by ~5 MW of waste heat piped across the street from a data-dense building,120Notre Dame’s server racks heat South Bend’s municipal greenhouse, saving the city about $70,000 a year,121and in the UK a 28 kW micro data center cut a public swimming pool’s gas bill 62%.122 A regional policy group, ReImagine Appalachia, argues for exactly this model here — using data center heat for schools, public buildings, or greenhouses on former mine land.126 For Pikeville, heating the town is not realistic; heating an adjacent greenhouse complex, pool, or campus building is — if heat-recovery plumbing is designed in from day one, which is a reasonable thing to raise while a Development Agreement is still being negotiated.

Where water became a problem — and where it didn't

  • The Dalles, Oregon:Google’s data centers used 355.1 million gallons in 2021 — 29% of the entire city’s water — a fact disclosed only after a 13-month public-records fight with the local newspaper.105 Google also funded $28.5 million of city water infrastructure.106Lesson: the problem wasn’t only the volume — it was the secrecy.
  • Newton County, Georgia:residents 1,000 feet from Meta’s construction site reported wells running dry and sediment; Meta’s commissioned study found no connection, the county did no pre-construction well survey, and causation remains unresolved.85
  • Mesa & Goodyear, Arizona: desert cities negotiated tiered water caps (1 up to 4 million gallons/day in Mesa)108 and in Goodyear, Microsoft agreed to switch its design to air cooling and contributed $36M toward a wastewater plant.109
  • Memphis: xAI pledged an $80M wastewater recycling plant (13 million gallons/day design) to stop drawing on the drinking-water aquifer — groundbreaking happened, though the project was later paused, a reminder that pledges need enforceable timelines.110
  • Mount Pleasant, Wisconsin (the quiet success): Microsoft’s closed-loop campus uses 2.8M gallons a year in Phase 1 — less than many ordinary industrial customers on the same utility.107
  • Loudoun County, Virginia: the water utility delivers reclaimed (treated wastewater) through purple pipe for data center cooling — over 750 million gallons in 2025 — sparing the same volume of drinking water.111Google’s Georgia site similarly cools with recycled municipal effluent.112